Release Work Order

Explanation

This activity is used to change the status of a work order to Released.

Prerequisites

Before the status can be changed, the following must have been completed:

System Effects

Window

Prepare Work Order

Related Window Descriptions

Prepare Work Order

Procedure

Use the following procedure to change the status:

  1. Open the Prepare Work Order window. Right-click, point to Work Order Status and click Released.
  2. If tools and/or facilities have been entered in the Tools and Facilities tab, the Enter Tools/Facilities Data for Work Order dialog box is opened. Select a site and a maintenance organization, click List to select suitable values.
  3. Click OK.