Explanation
Use this activity as the first step to move a serial object from the
repair workshop to facility.
Prerequisites
Before a serial object is moved to facility, the following must have
been completed:
- The serial object must have been moved to the repair workshop via a repair
work order.
- The current repair work order must have been retrieved in the window.
System Effects
N/A
Window
Report In
Work Order
Related Window Descriptions
Report In Work Order
Procedure
Use the following procedure to move a serial object to facility:
- In
Report In Work Order, select the Place Serial in
Equipment Structure
operation. Information on the object to be moved is displayed in the lower part of the