Set Invitation to Tender Baseline

Explanation

This activity is used to set the invitation to tender baseline. Once a Request For Quotation (RFQ) for a sub contract is ready for submission, the invitation to tender baseline should be set. This is to ensure that we keep track of all required details on the submitted sub contract. It will later be possible to compare the invitation to tender baseline with both the contract baseline and the current revision of the sub contract.

Once the invitation to tender baseline is set, the active revision will be frozen and changes to this revision will no longer be allowed.

Prerequisites

System Effects

Window

Sub Contract
Sub Contracts

Related Window Descriptions

Sub Contract
Sub Contracts

Procedure

  1. Open the Sub Contract window or the Sub Contracts window.
  2. Query (F3) for the necessary sub contract.
  3. Right-click and then click Set Invitation Baseline.
  4. A message requiring approval of the step appears, click Yes.