Perform Due Calculation for LLP Tasks

Explanation

This activity is used to perform the due calculation for LLP tasks for a given serial. The calculation will be done for the serial, based on the registered average operational value per month and the life limited information defined for the serial. In addition, the due calculation will calculate the remaining life and drop-dead date and create a LLP task for the given serial, provided the serial part number is defined as a life limited part and it has reached the days of the forewarning period.


Apart from manually performing the due calculation for a serial (as described in this activity), scheduled tasks exist to automatically calculate due dates for all life limited serials. The Life Limited Part Calculation scheduled task will be used to calculate the life limit of all serials defined as life limited parts. For more information on the scheduled tasks, refer to the activity Adjust and Verify Background Job for Calculations of LLP Tasks.
 

Prerequisites

System Effects

Window

Serial Maintenance
Task Summary
Change Work Scope Tasks

Related Window Descriptions

Serial Maintenance
Serial Maintenance/Life Limited Serials
Task Summary
Task Summary/LLPs
Change Work Scope Tasks
Change Work Scope Tasks/LLPs

Procedure

Use the following procedure to run the due calculation for LLP tasks for a serial.

  1. Open the Serial Maintenance window.
  2. Query (F3) for the serial for which you will run the task calculation.
  3. Right-click anywhere in the header of the window and then click Perform Due Calculation to open the Perform Due Calculation dialog box.
  4. Select the LLP Calculation check box to calculate LLP tasks.
  5. If you want to perform task calculation for all serials in the serial structure, select the Calculate Entire Structure check box.
  6. To perform the task calculation as a background job, select the Run in Background check box.
  7. Click OK.

If IFS/Complex MRO is used, the following procedure can be used to calculate due dates for the LLP tasks which are to be performed during a shop visit:

  1. Open the Task Summary window or the Change Work Scope Tasks window and query (F3) for the overhaul object and/or the MRO work order number you want.
  2. Right-click anywhere in the header, and then click Perform Due Calculation.
  3. The calculated due dates can be viewed in the LLPs tab found in the Task Summary window and in the Change Work Scope Tasks window.