Net Project Material

Explanation

Use this function to perform automatic netting of parts demanded by the project (and delivery project). Netting reserves these parts based on the need date and availability. However, all manually reserved material are not included in the netting.

The Netting checkbox for a demand line should be checked if netting is to be performed for the part. If it is unchecked, then the part will not not be included in the netting.

It is possible to run netting online or as a background job. If a delivery project exists, it is also possible to run the Gross Requirements calculation to register the material need of the delivery project which can also be included in the netting.

Note: Netting does not use any Project Netting Groups (PNG). These groups belong to PMRP and are not a part of the Netting concept.

Prerequisites

System Effects

Window

Project Navigator

Project

Projects

Delivery Projects

Related Window Descriptions

Project Navigator

Project

Projects

Delivery Projects

Procedure

  1. Query for the project and select it. Right-click, point to Netting and then click Net Project Material.