Insert Activities

Explanation

After the project structure is created, you should register the activities related to the subprojects. See About Activities for more information on activities. All cost and hours are accumulated on the activities, and cannot be assigned directly to a subproject.

Objects, for example tasks, work orders, document packages, and purchase orders, can be connected to activities. These objects report progress, costs and hours to the activity. In addition, resources can be allocated to activities. An activity's committed and actual cost/hours can also be updated through IFS/Project Reporting.

Prerequisites

System Effects

Window

Activities
Activity
Project Navigator/
Activity List
Project Navigator/Activity

Related Window Descriptions

Activities
Activity
Project Navigator/Activity List
Project Navigator/Activity

Procedure

Activity/Activities

  1. Create a new activity.
  2. Enter the Project ID using the List of Values option or F8 is available.
  3. Enter the Sub Project ID using the List of Values option or F8 is available.
  4. Enter the Activity ID.
  5. If the Short Name is left blank, the system will generate a short name for you.
  6. Enter an Activity Description, Early Start, and an Early Finish date.
  7. Save the new record.

Project Navigator/Activity List

  1. Select the desired parent subproject in the graphical display.
  2. Select the Activity List tab, and create a new record.
  3. Enter Activity ID.
  4. Enter an Activity Description, Early Start, and an Early Finish date..
  5. Save the new record.

Project Navigator/Activity

  1. Select the desired parent subproject in the graphical display.
  2. Go to the Activity tab, and create a new record.
  3. Enter Activity ID.
  4. Enter an Activity Description, Start, and Finish (early start and early finish) dates.
  5. Save the new record.