Connect/Disconnect Contract Change Orders

Explanation

Use this activity to connect contract change order forecasts to a budget/forecast version.

Prerequisites

System Effects

Window

Project Forecast

Related Window Descriptions

Project Forecast
Forecast Connection
Contract Change Order

Procedure

Use the following procedure to connect a contract change order forecast to the selected budget/forecast version:

  1. Open the Project Forecast window, query for the project budget/forecast version for which you want to connect a contract change order forecast.
  2. Right click on the window, click Forecast Connection. The dialog box opens up.
  3. Select the Contract Change Orders tab.
  4. Click New to enter a new line.
  5. In the Change Order No field, use the List button to select a previously created contract change order forecast that you want to connect to the selected budget/forecast version.
  6. Click OK.

Note. Alternatively, it is also possible to use Select Batch to select more than one contract change order forecast.

Use the following procedure to disconnect a contract change order forecast from a selected budget/forecast version:

  1. Open the Project Forecast window, query for the project budget/forecast version from which you want to disconnect the contract change order forecast. 
  2. Right click on the window, click the Forecast Connection menu option. The Forecast Connection dialog box will open.
  3. Select the Contract Change Orders tab.
  4. Select the required row and click Remove.
  5. Click OK.

Use the following procedure to update a contract change order forecast in a selected budget/forecast version:

  1. Open the Project Forecast window, query for the project budget/forecast version for which you want to update the contract change order forecast. 
  2. Right click on the window, and click Forecast Connection. The dialog box opens up.
  3. Select the Contract Change Orders tab.
  4. Select a row and click Update.
  5. Click OK.