Generate Unfinished Activity Work Items
Usage
Use this dialog box to generate a list of activities where work remains to be
completed. The list can be generated for a project, sub project or a specific
activity. Per default, the generation is executed as a background job for
released and completed activities. It is possible to configure
these settings:
- If the check box Exclude Sub Levels, is selected, the
generation will not include the sub structure of the sub project defined in
the dialog box. If the check box is not selected, the generation will
include the defined sub project and all its underlying levels.
- If the check box Exclude Released Activities, is selected,
the generation will exclude all activities in status Released and
only include activities in status Completed. If the check box is not
selected, released and completed activities are included in the generation.
- If the check box Run in Background, is selected, the generation
will be executed as a background job. If the check box is not selected, the
generation will be executed online. When the generation is completed, it
will be possible to populate the result of the generation in the
Unfinished Activity Work window.
Activity Diagrams
Execute Activity
Activities
Generate Unfinished Activity Work Items