Disconnect Purchase Requisition Line from Project
Activity
Explanation
This activity is used to disconnect a manually connected
purchase requisition line from the project activity. You can perform this
activity from the Purchase Requisition window itself.
Note that it is also possible for you to disconnect
manually connected purchase requisition lines using the
Connect/Disconnect
dialog box (accessible from the Project Info/Connections tab).
Please refer to the activity Connect Existing Object to Activity.
Prerequisites
- The project connection must have been manually
created.
- The purchase requisition line must not have the PO
Created or Request Created status.
System Effects
- The purchase requisition line will be disconnected
from the project activity.
- The project's pre-posting will be removed. (It is possible to have
postings that are not connected to project activities. Pre-posting for the project code part and the activity sequence will be removed,
but pre-posting for all the other code parts will remain.)
- The purchase requisition line will no longer appear as a connection on
the Project Info/Connections tab.
- The purchase requisition line demand code will be changed
back to the demand code that existed prior to connecting the project activity,
i.e., to Inventory Order or Non-Inventory Order.
Window
Purchase
Requisition
Related Window Descriptions
Purchase Requisition
Procedure
- Open the Purchase Requisition window,
and query for the relevant purchase requisition.
- Select the required purchase requisition line.
Details regarding the activity to which the purchase requisition line
is connected can be viewed on the line itself.
- Right-click on the selected line, point to Project
Connections and then click Disconnect from Activity; the line will be
disconnected from the project activity.