Connect Purchase Order Line to Project Activity

Explanation

Use this activity to manually connect a purchase order line to a project activity from the purchase order line itself. This activity is performed to obtain the cost of the project activity of goods being requested for the project through the purchase order.

Note that you can manually connect an existing purchase order line to a project activity also from the project activity. (Refer to the activity Connect Existing Object to Activity). Another alternative is to handle a project demand by procuring material against the miscellaneous demand on the project activity. In such situations, the connection between the project activity and the purchase order line would be system generated.

Of the above alternatives, manually connecting a purchase order line to a project activity from the line itself (described in this activity), is the most efficient process of handling purchase orders for a project activity. This is because it excludes the need to access the project client when handling project supplies. If you have a demand against inventory for a project activity, you can supply this by creating a purchase order for that demand in a standard manner, and connecting it to a project activity from the purchase order line itself.  

Note that you will be allowed to receive customer owned parts from a single customer to a project that is connected to another customer. 

Prerequisites

System Effects

As a result of this activity:

Window

Purchase Order

Related Window Descriptions

Purchase Order
Connect to Activity

Procedure

  1. Open the Purchase Order window, and query for the relevant purchase order.
  2. Select the required purchase order line, right-click, point to Project Connections and then click Connect to Activity. The Connect to Activity dialog box opens. 
  3. To select the activity to which you want to connect the purchase order line, click on the Program ID field (or the Project ID field if your project does not have a program ID).
  4. Click List, and use the List of Values to select the program ID pertaining to the activity you want to select.
  5. You can continue to specify the criteria for the activity you want to select, by clicking on the Project ID, Sub Project ID, and Activity ID fields, and then selecting values from the List of Values.
  6. Alternatively, you can enter the activity sequence in the Activity Sequence field, or select it from the List of Values. (The activity sequence can be obtained from the Project Info/Activity/Details tab.) 
  7. Click OK to save the record.