Peg or Unpeg Material Demand

Explanation

This activity is used to manually connect or remove the connection between existing supplies and maintenance order material demands or work order material demands. The purpose of this connection (pegging) is to allow automatic allocation of supplies to the maintenance order material demands or work order material demands as soon as the material arrives in inventory.

Prerequisites

System Effects

Window

Maintenance Order
Prepare Work Order
Report In Work Order

Related Window Descriptions

Maintenance Order
Maintenance Order/Maint. Order Str.
Maintenance Order/Maint. Order Str./Material Required
Maintenance Order/Exec. Logic
Maintenance Order/Exec. Logic/Material Required
Prepare Work Order
Prepare Work Order/Materials
Report In Work Order
Report In Work Order/Materials
Manual Pegging of Maintenance Order Material Line
Manual Pegging of Work Order Material Line

Procedure

Peg Material Demands:

Follow this procedure to perform manual pegging on a maintenance order having the Simplified Work Order or Work Order distribution types:

  1. Open the Maintenance Order window and search for the necessary maintenance order.
  2. Click the Maint Order Str. tab. Select the relevant structure item in the graphical maintenance order structure and then click the Material Required sub tab.
  3. Right-click on the part line and then click Manual Pegging. The Manual Pegging of Maintenance Order Material Line window opens.
  4. In the table, all open purchase orders for the selected part will be displayed. Select the relevant purchase order line.
  5. In the Qty Pegged field, enter the quantity of material you want pegged.
  6. Save the information (F12).
  7. Verify that the quantity you entered is displayed in the Qty Pegged field for the relevant part line in the Material Required sub tab. You can also verify whether the reserved quantity is reflect on the demand line by right-clicking on the part line and then clicking Inventory Part Availability Planning.

Follow this procedure to perform manual pegging on a maintenance order having the Execution Logic Structure distribution type:

  1. Open the Maintenance Order window and search for the necessary maintenance order.
  2. Click the Exec. Logic tab. Select the relevant node item in the graphical ELS structure and then click the Material Required sub tab.
  3. Right-click on the part line and then click Manual Pegging. The Manual Pegging of Maintenance Order Material Line window opens.
  4. In the table, all open purchase orders for the selected part will be displayed. Select the relevant purchase order line.
  5. In the Qty Pegged field, enter the quantity of material you want pegged.
  6. Save the information (F12).
  7. Verify that the quantity you entered is displayed in the Qty Pegged field for the relevant part line in the Material Required sub tab. You can also verify whether the reserved quantity is reflect on the demand line by right-clicking on the part line and then clicking Inventory Part Availability Planning.

Follow this procedure to perform manual pegging for the material on a work order:

  1. Open the Prepare Work Order or Report In Work Order window and search for the necessary work order.
  2. Click the Materials tab.
  3. Ensure that the relevant material requisition order number is selected in the Order No field.
  4. In the table, select the relevant material line, right-click and then click Manual Pegging. The Manual Pegging of Work Order Material Line window opens.
  5. In the Purch Order tab, all open purchase orders for the selected part will be displayed. Select the relevant purchase order line.
  6. In the Pegged Supply Quantity field, enter the quantity of material you want pegged.
  7. Save the information (F12).
  8. Verify that the quantity you entered is displayed in the Quantity Pegged field for the relevant material line in the Materials tab. You can also verify whether the reserved quantity is reflect on the demand line by right-clicking on the material line and then clicking Inventory Part Availability Planning.

Unpeg Material Demands:

Follow this procedure to unpeg a previously pegged material demand on a maintenance order having the Simplified Work Order or Work Order distribution types:

  1. Open the Maintenance Order window and search for the necessary maintenance order.
  2. Click the Maint Order Str. tab. Select the relevant structure item in the graphical maintenance order structure and then click the Material Required sub tab.
  3. Right-click on the part line and then click Manual Pegging. The Manual Pegging of Maintenance Order Material Line window opens.
  4. In the table, all open purchase orders for the selected part will be displayed. Select the relevant purchase order line.
  5. In the Qty Pegged field, enter the quantity of material you want unpegged from the supply.
  6. Save the information (F12).
  7. In the Material Required sub tab verify that the quantity in the Qty Pegged field has reduced by the value you entered.

Follow this procedure to remove the reservation of a part from a maintenance order having the Execution Logic Structure distribution type:

  1. Open the Maintenance Order window and search for the necessary maintenance order.
  2. Click the Exec. Logic tab. Select the relevant structure item in the graphical ELS structure and then click the Material Required sub tab.
  3. Right-click on the part line and then click Manual Pegging. The Manual Pegging of Maintenance Order Material Line window opens.
  4. In the table, all open purchase orders for the selected part will be displayed. Select the relevant purchase order line.
  5. In the Qty Pegged field, enter the quantity of material you want unpegged from the supply.
  6. Save the information (F12).
  7. In the Material Required sub tab verify that the quantity in the Qty Pegged field has reduced by the value you entered.

Follow this procedure to unpeg a previously pegged material demand on a work order:

  1. Open the Prepare Work Order or Report In Work Order window and search for the necessary work order.
  2. Click the Materials tab.
  3. Ensure that the relevant material requisition order number is selected in the Order No field.
  4. In the table, select the relevant material line, right-click and then click Manual Pegging. The Manual Pegging of Work Order Material Line window opens.
  5. In the Purch Order tab, all open purchase orders for the selected part will be displayed. Select the relevant purchase order line.
  6. In the Pegged Supply Quantity field, enter the quantity of material you want unpegged from the supply.
  7. Save the information (F12).
  8. In the Materials tab verify that the quantity in the Quantity Pegged field has reduced by the value you entered.