Create DOP Structure Manually
Explanation
Use this activity to create a DOP order manually. This is an alternative to copying a
structure from an existing DOP or BOM structure.
Prerequisites
- The status of the parent DOP order may not have reached the
Released state. The DOP structure cannot be created for parts with a recipe structure.
System Effects
As a result of this activity:
- A new DOP order is created in the Created state. The
Structure
Changed check box is selected for the parent DOP order and the DOP header.
- If the DOP header is project specific, DOP Orders that
are created will be tagged with Project ID and Activity Sequence.
- A valid routing revision and a plannable or buildable routing
alternative will be added for each DOP order. If no buildable or plannable routing
alternative exist for the part a DOP log is created. If the routing is serial effective
and no serial numbers are reserved for the DOP order a DOP log is created.
- If the revised start date is not manually entered it is
calculated for the new DOP order in the structure, due to the revised due date and
lead-time, where the lead-time is depending on lot size and routing revision and
alternative.
Window
DOP Header
Related Window Descriptions
DOP Header
DOP Header/Structure
DOP Order
DOP Order/Components
Procedure
- Open the DOP Header window.
- Retrieve the parent DOP order for which to create a structure in
DOP
Header/Structure or
DOP Order/Components.
- To add a DOP order, double-click to the left of the
table or click New.
- Enter the part number of the DOP order in the Part No field. Use
the List of Values
to select from available parts.
- Enter the quantity needed to manufacture one parent part in the Qty per Assembly
field.
- Click Save.
- Repeat steps 2-5 for each DOP order to add.
Note: To be able to create structure for the part, e.g.
Add
Branch, you have to use the right mouse button option Plan first. This
changes the status from Created to Unreleased for the DOP Order.