Change Revision and/or Alternative
Explanation
This activity is used to change a revision and/or alternative for a DOP
order.
Prerequisites
- Another revision and/or alternative having a Plannable
or Buildable status must exist. When the DOP order is released, the status
of its supply shop orders must be Planned, Released or Reserved.
- Pegged purchase orders must not exist.
System Effects
As a result of this activity:
- The revision and/or alternative is
changed for the DOP order.
- The revised start date is recalculated depending on revised due
date, lead-time and lead-time offset, where the lead-time is depending on lot size and
routing revision and alternative. When the DOP order is
released, the operations of its supply shop orders are adjusted.
Window
DOP Header
DOP Order
Related Window Descriptions
DOP Header
DOP Order
DOP Header/Structure
DOP Order/Detail
Procedure
- Select the DOP order for which the revision and/or alternative needs to be changed,
either from the DOP Order window, DOP Order/Tree Structure tab,
DOP Header/Structure tab or the DOP Header/Tree Structure tab.
- Right-click and click Change DOP Structure > Change Revision and/or Alternative.
- In the dialog box that opens, select an available revision number from the List of Values.
- Click OK.