Explanation
Use this activity to add a DOP structure branch for a specific
DOP order. The new DOP structure branch can either be created from BOM or copied from
another DOP structure.
Prerequisites
- The Create Pegged attribute for the DOP order must
be set to Pegged Orders.
- When the parent DOP order is released, the status
of its supply shop order must be Planned, Released or Reserved.
- Pegged purchase orders must not exist.
System Effects
As a result of this activity:
- A DOP branch is added to the
DOP structure. The status of the DOP orders are set to Unreleased. The
Structure
Changed check box is selected for the specific DOP order and the DOP header.
If the parent DOP order is Released, a new component is added to its supply shop
orders.
- If the DOP order in consideration is project specific
the new DOP branch added will be tagged with Project ID and Activity Sequence.
- When you create a DOP structure, any intermediate steps in the
structure are deleted. Parts with planning methods K and P, Blow through and Phantom parts,
are considered intermediate steps.
- If a DOP order is serial-effective, the breaking-down stops at the DOP order
level and a log is created. The log is displayed in
DOP Logs.
If you have allowed an automatic release of DOP orders, higher levels in the structure are
not released.
- When creating a DOP structure which includes a phantom part, the DOP
order is created for the phantom part if there is enough inventory to
fulfill the order. Phantom parts are needed to net as and when the DOP order
is created to avoid material shortages in the future.
- If adding a DOP structure from BOM, a valid routing revision and
a plannable or buildable routing alternative are added for each DOP order. If no
buildable or plannable routing alternative exists for the part, a DOP log is created;
however, the creation of the structure continues. If copying a DOP structure from another
DOP structure, the routing revision and routing alternative are
copied to each DOP order. If the routing is serial-effective and no serial numbers
are reserved for the DOP order, a DOP log is created; however, the creation of the
structure continues.
- When creating the new DOP structure from BOM the revised due date
and the revised start date are calculated for each added DOP order in the structure,
depending on revised due date and revised start date of the parent DOP order, lead-time
and lead-time offset, where the lead-time is depending on lot size and
routing revision and alternative.
Window
DOP Header
DOP Order
Related Window Descriptions
DOP Header
DOP Header/Structure
DOP Header/Tree Structure
DOP Order
Procedure
From the DOP Header
window:
- Open the DOP Header window.
- Retrieve the DOP header for the DOP order for which to add a
branch structure, then click the
Structure tab and locate the
actual DOP order.
- Right-click anywhere in the header, point to
Change DOP Structure, and then click Add Branch. The
Create DOP Structure/Routings dialog box will be displayed.
- Specify whether you want to add a branch structure from BOM or
from another DOP structure by selecting either
Create DOP Structure from BOM or
Copy
DOP Structure from other DOP Structure.
- To create the DOP structure from BOM, select the Revision No and
Alternative No. Click List to select from available revisions and
alternatives. The default revision is displayed in the fields.
- To copy the DOP structure from an existing DOP structure, enter
the DOP order whose structure is to be used in the DOP ID field.
Click List
to select from available orders.
- Click OK.
From the
DOP Order window:
- Open the
DOP Order window.
- Retrieve the DOP order for which to add a branch structure.
- Right-click anywhere in the header, point to
Change DOP Structure, and then click Add Branch. The
Create DOP Structure/Routings dialog box will be displayed.
- Specify whether you want to add a branch structure from BOM or
from another DOP structure by selecting either
Create DOP Structure from BOM or
Copy
DOP Structure from other DOP Structure.
- To create the DOP structure from BOM, select the Revision No and
Alternative No. Click List to select from available revisions and
alternatives. The default revision is displayed in the fields.
- To copy the DOP structure from an existing DOP structure, enter
the DOP order whose structure is to be used in the DOP ID field.
Click List
to select from available orders.
- Click OK.
From the tree graph of (DOP Order/Tree Structure or
DOP
Header/DOP Structure):
- Select the DOP Order to which to add a branch.
- Right-click on the required object, point to
Change DOP Structure,
and then click Add Branch.
- Enter the required data in the
Create DOP Structure/Routings
dialog box which appears.
- Click OK.