Cost Elements Planned Cost Details

[About Project Cost Elements] [About Material Handling] [To Asset Procurement]

Usage

Use this dialog box to view, add or manually update the details of cost that can be entered per project demand part.

Initially if cost details can be seen in this dialog box the planned cost of the demand part has been retrieved from the price defined by a primary supplier; if a primary supplier and price have been defined. The cost element(s) for the planned costs will be as specified in the posting control set up for the particular company.

If a primary supplier or supplier price definition does not exist, the planned cost will be the inventory value of the inventory part corresponding to the demand part. If an inventory value definition does not exist, the planned cost will be the estimated material cost of the inventory part.

Activity Diagrams

Handle Material Demand

Activities

Add/Modify Planned Cost Details on ERMPL Demand Part