Isolation and Permit Planning

[About Permits] [About Work Order] [About PM Actions] [About Isolation and Permit Planning] [To Equipment and Personal Safety Management]

Usage

Use this window to graphically view as well as to reschedule isolation orders and permits. The window is divided into two sections:

Frame Settings: Contains the calendar unit you wish to view the graph in, i.e., Hour, Day and Week; and the time period for which you want to view the records. The Frame Settings area can be hidden if you require more space to view the graph.

Graph area: The graph area displays nodes related to isolation orders, permits and connected work orders. Permits and work orders are denoted by a uniformly colored horizontal bar: where as isolation orders are denoted by two horizontal bars, one embedded within the other: . The colors of the bars represent the status of the isolation order, permit and work order . To change the colors right-click on the graph area and click Properties. Select the relevant colors in the General/Status Color tab. In addition the dialog box also contains the following information that you can change:

Further more you can change the status of the isolation order and permit by using the Isolation Order Status and Permit Status right mouse button options.

Activity Diagrams

Isolation Order and Permit Planning

Activities

View Isolation Orders and Permits
Reschedule Isolation Orders and Permits