Disable Revision Control

Explanation

Use this activity to disable revision control on an existing PM action. A PM action revision that is in active status can only be updated with restriction if revision control is enabled and major changes such as entering new jobs, changing criteria associated with maintenance plan, changing maintenance organization, etc, cannot be performed. You can make any changes to the same PM action without having to create new PM action revisions by disabling revision control.

Prerequisites

A PM action revision in Active or Obsolete status should exist in the system, revision control should be enabled.

System Effects

As a result of this activity you need not to create new revisions for doing major changes in the used PM action and a journal entry is created that the revision control has been disabled.
 

Window

Separate PM Action
Route PM Action

Related Window Descriptions

Separate PM Action
Route PM Action 
Create New Revision for PM

Procedure

  1. Open the Separate PM Action or Route PM Action window, and query for the PM action for which you want to disable the revision control. (Alternatively you can directly query for the revision itself).
  2. Right-click and then click Disable Revision Control.