Use Current Buildable Revision when the Start Date is Past Due
Explanation
This activity is used to determine whether a shop order or a shop order requisition created with a past due start date should be based on the current buildable revision or if the buildable revision of the past due start date should be used.
Prerequisites
This activity requires that shop order requisitions or shop orders are created with a past due start date.
System Effects
Shop order requisitions and shop orders with past due start dates will be based on
the active revision on the current date when created.
Window
Site
Related Window Descriptions
Site/Manufacturing
Procedure
- Open the Site window and click the
Manufacturing
tab.
- Query for the required site.
- On the Manufacturing tab, select the Use Current Buildable Revisions for Supplies with Past Due Start Dates check box, to use the revision of the current date for shop order requisitions and shop orders with past due start dates.
- Save the record.