Start Setup
Explanation
This activity is used to register that a set up has started on one or several
operations. It is possible to register both labor and machine time.
The start time and the stop time of a setup will be recorded. The clocking
sequence is a unique number that will be set for each clocking record that is
created, however the same clocking sequence will be set for all operations that
are started at the same time.
From time clock, you can start setup for only one
operation at a time.
Prerequisites
- The status of the operation is not Planned or Closed.
- The status of the shop order should not be Parked.
- Neither a production nor set up activity is already running for the
particular operation.
- To start labor time, a labor class must be connected to the operation in
the Shop Order window.
- To start machine time, a valid resource must exist on the work center.
- If Reporting Mode has been set to Employee Reporting on
the used site at least one Employee must be entered in order to
report labor time.
- If an employee setup competency requirement
exists for the operation, and the competency check for the site is
mandatory, then the reporting employee(s) must have those competencies.
- To report from time clock, employee should be a
time clock user. When reporting as a team, all the employees in the team
should be time clock users.
System Effects
- If the Machine Time checkbox has been selected, a Machine
Clocking will be created and the start time recorded on it.
- If the Labor Time checkbox has been selected, one Labor
Clocking will be created for each Employee that has been entered in the
Employee List and the start time will be recorded on it. If no
Employee is entered, one clocking will be created.
- The start time will be recorded on the clocking.
The clockings can be viewed in the
Clockings tab.
- The operation will be marked with a monkey wrench symbol to
the left in the operation list. If several operations was started together
the monkey wrench will be complemented with a chain link.
- If the operation had an exclamation mark for
interruption, this symbol is now removed.
- The status of the operation is set to Setup Started.
- If the employee or team was running an indirect job, this will be
stopped.
- If a machine clocking is already running on the resource where this one
is started and the Allow Concurrent Operations check box in the
Work Center window is cleared this machine clocking will be
stopped.
- The selected resource will be set as the preferred resource for the
operation.
Window
Shop Floor Workbench
Time Clock
Related Window Descriptions
Shop Floor Workbench
Start Setup
Time Clock
Procedure
- Open the Shop Floor Workbench window. If Reporting Mode
has been set to Employee Reporting on the used site an employee or
team must have been entered in the Enter As dialog box.
- Click Refresh. The operations will be displayed according to the
filter that is being used.
- Select the operation lines for which you wish to
start setup, and click Start Setup.
- The
Start Setup dialog box will be
opened. Based on the data entered in the
Shop Order window,
Machine Time and Labor Time options will be selected. You
can change the values if you want to.
- Choose the resource which on the operation will be set up in the
Resource list.
- If run in Employee Reporting mode, enter the employees that will
work with the operation in the Employee table. If a team is entered in
Shop Floor Workbench, the employees currently in the team is displayed and may not
be changed. If run in Anonymous
mode, enter the crew size manually.
- Click OK. The start time can be viewed in the Clockings
tab.
- Click the Start Setup. The start time can
be viewed in the
Clockings tab.
To perform this activity from Time Clock
- Click the Start Setup button in Time
Clock.
- Enter the Employee ID or the Team.
- Enter the Operation ID you want to start
setup for.
- If machine setup time exists for the operation,
Machine Time will be automatically set to Yes. Set it to No
if you do not want to start machine setup.
- Choose the resource on which the operation will be set up in the
Resource ID.
- If the existing clockings for the employee should
be stopped, select Yes in Stop Emp Clockings. The default
value is set based on the value of Allow Concurrent Operations for
the employee in Manufacturing Labor Class/Employee tab.
- Click OK.