Reschedule Shop Order Operation Using Drag-and-Drop

Explanation

This activity is used to reschedule a shop order operation using drag-and-drop functionality from a visualization chart.

Prerequisites

System Effects

If the newly given start date is later than the original activity will result in:

If the newly given finish date is earlier than the original activity will result in:

Window

N/A

Related Window Descriptions

Reschedule Shop Order (Operation)

Related Visualization Chart Descriptions

Machine Operation Load In Standard Hours
Shop Order Machine Load
Labor Operation Load In Standard Hours
Shop Order Labor Load

Procedure

From Shop Order Machine Load and Shop Order Labor Load:

  1. Open a visualizer enabled window and query for the site needed.
  2. If the Data View is displayed, click Visualization View on the title bar.
  3. Right-click and select Select Visualization. The Select Visualization dialog box will be opened.
  4. Double-click Shop Order Machine Load or Shop Order Labor Load.
  5. Select the segment representing the shop order or shop order operation you want to reschedule to a new date/time.
  6. Click and hold the left mouse button while moving the cursor. Release at the time slot to which you want the order/operation to be rescheduled. The Reschedule Shop Order (Operation) dialog box will be opened.
  7. If the new date/time is earlier than the original you can optionally edit the Finish Date. If the new date/time is later than the original you can optionally edit the Start Date.
  8. If you are rescheduling an operation that has preceding or succeeding operation and you want to avoid a gap between the operations, select the Compress Operations option.
  9. Click OK.

From Machine Operation Load in Standard Hours and Labor Operation Load in Standard Hours:

  1. Open a visualizer enabled window and query for the site needed.
  2. If the Data View is displayed, click Visualization View on the title bar.
  3. Right-click and select Select Visualization. The Select Visualization dialog box will be opened.
  4. Double-click Machine Operation Load in Standard Hours or Labor Operation Load in Standard Hours.
  5. Right-click and click X-Axis/Include Non-Load Days.
  6. Select a segment representing the shop order operation you want to reschedule to a new date/time.
  7. Click and hold the left mouse button while moving the cursor. Release at the time slot to which you want the operation to be rescheduled. The Reschedule Shop Order (Operation) dialog box will be opened.
  8. If the new date/time is earlier than the original you can optionally edit the Finish Date. If the new date/time is later than the original you can optionally edit the Start Date.
  9. If you are rescheduling an operation that has preceding or succeeding operation and you want to avoid slack between the operations, select the Compress Operations option.
  10. Click OK.