Reschedule Shop Order Operation Using Drag-and-Drop
Explanation
This activity is used to reschedule a shop order operation using
drag-and-drop functionality from a visualization chart.
Prerequisites
- The Schedule Direction of the shop order may not be set to Manual Scheduling.
- The site of the shop order may not
be connected to CBS server. Drag-and-drop scheduling from the visualization
chart is not possible for CBS server solution enabled site's shop orders.
- When performed from Machine Operation Load in Standard Hours
or Labor Operation Load in Standard Hours the X-Axis
option must be set to Include Non-Load Days.
System Effects
If the newly given start date is later than the original activity will result in:
- Schedule Direction for the operation is set to Forward Scheduling and the operation will be rescheduled to start the first
available work date/time from the given value.
- Operations parallel to, and succeeding the rescheduled operation will
also be set to Forward Scheduling and rescheduled.
- If the Compress Operations checkbox is selected, the operation preceding the rescheduled operation will be set to
Backwards Scheduling
and rescheduled with a Finish Date
adjacent to the rescheduled
operations new Start Date.
- If the rescheduling is triggered for a shop order rather than a single
shop order operation, first open operation (having the lowest
Operation Seq No)
on the order will be rescheduled.
If the newly given finish date is earlier than the original activity will
result in:
- Schedule Direction for the operation is set to
Backwards
Scheduling and the operation will be rescheduled to
finish the last available work date/time before the given value.
- Operations parallel to, and preceding the rescheduled operation will
also be set to Backwards Scheduling and rescheduled.
- If the Compress Operations checkbox is selected the
operation succeeding the rescheduled operation will be set to
Forward
Scheduling and rescheduled with a
Start Date
adjacent to
the rescheduled operations new
Finish Date.
- If the rescheduling is triggered for a shop order rather than a single
shop order operation the last open operation (having the highest
Operation Seq No) on the order will be rescheduled
Window
N/A
Related Window Descriptions
Reschedule Shop Order (Operation)
Related Visualization Chart Descriptions
Machine Operation Load In Standard Hours
Shop Order Machine Load
Labor Operation Load In Standard Hours
Shop Order Labor Load
Procedure
From Shop Order Machine Load and Shop Order Labor Load:
- Open a visualizer enabled window and query for the site needed.
- If the Data View is displayed, click
Visualization View on the title bar.
- Right-click and select
Select Visualization.
The
Select Visualization dialog box will be
opened.
- Double-click Shop Order Machine Load or Shop Order Labor Load.
- Select the segment representing
the shop order or shop order operation you want to reschedule to a new
date/time.
- Click and hold the left mouse
button while moving the cursor. Release at the time slot to which you want
the order/operation to be rescheduled. The
Reschedule Shop
Order (Operation) dialog
box will be opened.
- If the new date/time is earlier
than the original you can optionally edit the
Finish Date.
If the new date/time is later than the original you can optionally edit the
Start Date.
- If you are rescheduling an
operation that has preceding or succeeding operation and you want to avoid a
gap between the operations, select the Compress Operations option.
- Click OK.
From Machine Operation Load in Standard Hours and Labor
Operation Load in Standard Hours:
- Open a visualizer enabled window and query for the site needed.
- If the Data View is displayed, click
Visualization View on the title bar.
- Right-click and select
Select Visualization.
The
Select Visualization dialog box will be
opened.
- Double-click Machine Operation Load in Standard Hours or
Labor Operation Load in Standard Hours.
- Right-click and click X-Axis/Include Non-Load Days.
- Select a segment representing
the shop order operation you want to reschedule to a new
date/time.
- Click and hold the left mouse
button while moving the cursor. Release at the time slot to which you want
the operation to be rescheduled. The
Reschedule Shop
Order (Operation) dialog
box will be opened.
- If the new date/time is earlier
than the original you can optionally edit the
Finish Date.
If the new date/time is later than the original you can optionally edit the
Start Date.
- If you are rescheduling an
operation that has preceding or succeeding operation and you want to avoid
slack between the operations, select the Compress Operations option.
- Click OK.