Receipt with Catch Unit Enabled Components

Explanation

This activity is used to handle receipt with Catch Unit (CU) enabled component parts in production schedules. A catch unit is enabled to allow a specific inventory part to manage two parallel units of measure. Information regarding both quantities, inventory and catch, are saved on every inventory transaction record.

Prerequisites

System Effects

Window

Production Receipt
Production Schedule By Line 
Production Schedule By Line Part

Related Window Descriptions

Production Receipt
Production Schedule By Line  
Production Schedule By Line Part
 

Procedure

From the Production Receipt window:

  1. Open the Production Receipt window. 
  2. Populate or query for the appropriate production line and part for which you want to report production.
  3. In the Sched Option list, select Scheduled or Unscheduled.
  4. In the Structure area, specify either the the structure/routing revision, or the structure/routing alternate.
  5. In the Backflush list, select Immediate Backflush or Defer Backflush.
  6. Next, enter the quantity to receive in the Quantity Received field. Material can be received into more than one inventory location. If the part is catch unit enabled, enter the catch quantity received in the Catch Quantity Received field.
  7. Select the Edit Components check box and save.
  8. The Production Receipt Material dialog box will appear.
  9. To change the quantity to issue, enter the desired value in Qty to Issue field.
  10. Save.
  11. To reserve the components before backflushing, select the component and then click Assign. The Production Receipt Reservation dialog box appears.
  12. In the Production Receipt Reservation dialog box, click Create. The Inventory Part Location dialog box appears.
  13. In the Inventory Part Location dialog box, select a location and click OK.
  14. In the Production Receipt Reservation dialog box, enter a value in the Qty Assigned field. Also enter the catch quantity that you want to reserve in the Catch Qty Assigned field.  
  15. Save and then click OK when the reservations are done.
  16. When you have finished editing and reserving the components, click OK to run the backflush.  

From the Production Schedule By Line window:

  1. Open the Production Schedule By Line window.
  2. Populate or query for the appropriate production line for which you want to report production.
  3. Select the production schedule line for which you want to report production. Right-click and then click Production Receipt.
  4. The Production Receipt dialog box appears.
  5. In the Production Receipt dialog box, specify how many parts you want to report and receive into inventory in the Qty Reported field. The scheduled quantity is the default value.
  6. In the Sched Option list, select Scheduled or Unscheduled.
  7. In the Backflush list, select Immediate Backflush or Defer Backflush.
  8. In the Structure area, specify the structure revision and the structure alternate. If desired, you can specify the routing revision and the routing alternate.
  9. In the Location area, select the Complete check box to create a complete production receipt.
  10. In the Location area, click in the Location No field and then click List to choose from different inventory locations.
  11. To edit components, click Components. The Production Receipt Material dialog box will appear.
  12. In the Production Receipt Material dialog box, type a value in the Qty To Issue field.
  13. To change the components, click New. In the Part To Issue field, enter or select an available part from the List of Values. Next, enter a value in Qty to Issue field.
  14. Save.
  15. To reserve the components before backflushing, select the components and then click Assign. The Production Receipt Reservation dialog box will appear.
  16. In the Production Receipt Reservation dialog box, click Create. The Inventory Part Location dialog box will appear.
  17. In the Inventory Part Location dialog box, select a location. Click OK.
  18. In the Production Receipt Reservation dialog box, enter a value in the Qty Assigned field. Also enter the catch quantity that you want to reserve in the Catch Qty Assigned field.   
  19. Save and then click OK when the reservations are done.
  20. When you have finished editing and reserving the components, click OK  to run the backflush.

From the Production Schedule By Line Part window:

  1. Open the Production Schedule by Line Part window.
  2. Populate or query for the appropriate part for which you want to report production.
  3. Select the production schedule line for which you want to report production. Right-click and then click Production Receipt. The Production Receipt dialog box appears.
  4. In the Production Receipt dialog box, specify how many parts you want to report and receive into inventory in the Qty Reported field. The scheduled quantity is the default value.
  5. In the Backflush list, select Immediate Backflush or Defer Backflush.
  6. In the Structure area, specify the structure revision and the structure alternate. If you want, you can specify the routing revision and the routing alternate.
  7. Select the Complete check box to create a complete production receipt.
  8. In the Location area, click in the Location No field and then click List to choose from different inventory locations.
  9. To edit the components, click Components. The Production Receipt Material dialog box appears.
  10. In the Production Receipt Material dialog box, enter a value in the Qty To Issue field.
  11. To change the components, click New. In the Part To Issue field, enter or select an available part from the List of Values. Next, enter a value in Qty to Issue field.
  12. Save.
  13. To reserve the components before backflushing, select the components and then click Assign. The Production Receipt Reservation dialog box will appear.
  14. In the Production Receipt Reservation dialog box, enter a value in the Qty Assigned field. Also enter the catch quantity that you want to reserve in the Catch Qty Assigned field.   
  15. Save and then click OK when the reservations are done.
  16. When you have finished editing and reserving the components, click OK  to run the backflush.