Create Shop Order Requisition Manually

Explanation

Use this activity to manually enter a shop order requisition. You can also generate a shop order requisition from MRP, Project MRP(PMRP), Master Scheduling, Order Proposals or Next-Level demand calculations.

Prerequisites

The part being requisitioned must have a valid part revision on the start date.

System Effects

As a result of this activity the system creates a shop order requisition. From this requisition, you can create a shop order. The system automatically generates the requisition number and suggested start date for manufacture.

Window

Shop Order Requisition
Shop Order Requisitions

Related Window Descriptions

Shop Order Requisition
Shop Order Requisitions

Procedure

  1. Create a new record.
  2. In the Part No field, enter the part for which you want to create the shop order requisition. Use the List of Values to select from the available parts.
  3. In the Quantity field, enter the quantity of the part you want to manufacture.
  4. In the Due Date field, enter the date when the part is needed.
  5. Save your changes.