This activity is used to approve a resource break which is in Proposed state. The status of the break converts to Unscheduled. In the case of sites using Constraint Based Scheduling (CBS), the break is then transferred to the Scheduling Server, although it is not yet scheduled there. In the case of Advanced Planning Board (APB) sites, only a state change occurs and these Unscheduled resource breaks will be loaded to the APB thereafter. Resource breaks are taken into account only when orders are scheduled using Constraint Based Scheduling (CBS), not when using the Shop Order Infinite Scheduler.
The activity requires the existence of a resource break in Proposed state.
As a result of this activity:
Resource Break
Resource Breaks