Disconnect Material Requisition Line from Project
Activity
Explanation
This activity is used to disconnect a manually connected material requisition
line from the project activity. You can perform this activity from the
Material
Requisition window itself.
Note that it is also possible to disconnect
manually connected material requisition lines using the Connect/Disconnect Object dialog box
(accessible from the Project Navigator/Connections tab). Please refer
to the activity description Connect Existing Object to Activity.
Prerequisites
- The project connection must have been manually
created.
- The material requisition line must be in the Planned
or Released status.
- The material requisition line must not have any previously
created financial transactions. That is, no issue of goods must have taken
place.
System Effects
As a result of this activity:
- The material requisition line will be disconnected
from the project activity.
- The project's pre-posting will be removed. (Note: Postings that are not
connected to project activities may exist. Pre-posting is removed only for
the project code part and the activity sequence; pre-posting for all other
code parts will remain.)
- The material requisition line will no longer appear
as a connection on the Project Navigator/Connections tab.
- If the material requisition line had the Project
Inventory supply code, this will be changed to Inventory Order.
Window
Material
Requisition
Related Window Descriptions
Material
Requisition
Procedure
- Open the
Material Requisition window,
and search for the relevant material requisition.
- Select the material requisition line you want to
disconnect. If required, you can view (on the material requisition line
itself) the details regarding the activity to which the material requisition
line is connected.
- Right-click on the selected line, point to Project
Connections, and then click Disconnect from Activity. The line will be
disconnected from the project activity.