Propagate CAMRO Interim Order Dates Downstream

Explanation

This activity is used when the start date of an MRO interim order header, or some disassembly or disposition order within that structure, has changed, to propagate the effects of that change through all the start and supply dates for the disassembly and disposition orders downstream (i.e., to all the disassembly and disposition orders after this point) in the order structure. The start and supply dates are calculated using the lead times specified for the parts.

Note: propagating dates downstream only impacts disassembly and disposition orders below the point of propagation. Repair and assembly orders are unaffected.

If this activity is initiated from the interim order header, dates will be calculated starting with the top-level disassembly order and ending with the lowest-level disassembly or disposition order. You can only propagate the dates from the interim order header if the interim orders have not yet been been released (i.e., while the header is in state Created). However, even after the interim orders have been released, the same result can be accomplished by propagating downstream from the top disassembly order.

On the other hand, if this activity is initiated from a specific disassembly or disposition interim order in the Tree Structure tab, the dates are calculated starting from that level and below in the interim order structure.

Prerequisites

The interim order header or interim order from which dates are being propagated cannot be in a Canceled or Closed state.

System Effects

The start and supply dates for all disassembly and disposition orders below the point of propagation are re-calculated from the new start date based on the part lead times.

Window

CAMRO Interim Order Structure

Related Window Descriptions

CAMRO Interim Order Structure

Procedure

In the CAMRO Interim Order Structure window, if propagating dates from the interim order header, use the following steps.

  1. From the Interim Header ID list, select the interim order structure for which you wish to propagate dates downstream.
  2. Verify that the state of this interim order header is not Canceled or Closed.
  3. Right-click and then click Propagate Dates Downstream to propagate the calculation of dates downstream through all the disassembly and disposition orders in the interim order structure.

If propagating dates from a specific interim order and down, use the following steps.

  1. Open the Tree Structure tab and select the interim order from where you wish to propagate the calculation of dates downstream.
  2. Verify that the state of the interim order is not Canceled or Closed.
  3. Right-click and then click Propagate Dates Downstream to initiate the propagation of dates downstream through all the disassembly and disposition orders in the interim order structure below the point of propagation.