Define Template for Work Progress

Explanation

This activity is used to define a work progress template. Work progress templates are used to calculate the progress on work orders, based on the status of work order operations. Each template will contain a list of the valid operation statuses for which you can define progress as a percentage. The following table shows a list of the valid operation statuses and default progress percentages:

Operation Status Cumulative Progress (%)
Cancelled 0
Finished 100
New 0
OnHold 0
Released 0
Started 0
WorkDone 0

The default percentage values for all operation statuses except Cancelled can be changed. When changing the progress values for operation statuses, the percentage values for the New, Released, Started, Work Done and Finished statuses must be in ascending order. For example, a progress template exists, with the following percentage values: 10% for Released, 20% for Started and 85% for Work Done. When changing the cumulative value for Started, you will not be allowed to enter a value below 10% or above 85%.

Prerequisites

N/A

System Effects

As a result of this activity, a work progress template is created and can be used to calculate progress on work orders.

Window

Operation Basic Data

Related Window Descriptions

Operation Basic Data
Operation Basic Data/Work Progress Template 

Procedure

  1. Open the Operation Basic Data window.
  2. Click the Work Progress Template tab and create a new record (F5).
  3. In the Template ID field, enter an identity for your template.
  4. In the Description field, enter a description of the template.
  5. Save the record (F12).
  6. In the table, all valid operation statuses appear automatically.
  7. In the Cumulative Progress (%) field, enter or update progress per operation status.
  8. Save the information (F12).