Report In Route Actions

Explanation

Use this activity to report in route actions. You need only to specify whether or not the actions are completed.

Prerequisites

Before the route actions are reported, the following must have been completed:

System Effects

As a result of this activity, the actions on a route work order are reported in.

Window

Report In Route

Related Window Descriptions

Report In Route

Procedure

  1. Mark the appropriate row.
  2. If the route action is done, select the Completed operation by using the right mouse button.
  3. If the route action is not done, select the Not Completed operation by using the right mouse button.