View Capability Indices
Graph
Explanation
This activity is used to view capability indices for a specific Control Plan
line and to view them graphically.
Prerequisites
The corresponding Control Plan must exist, and at least two
Analyses must be complete for this specific Control Plan line. The Capability
Indices check box for the Control Plan line must also be selected.
System Effects
As a result of this activity, capability indices
are calculated for a specific Control Plan line in a Control Plan. They are also
displayed
graphically.
Window
Capability
Indices Graph
Capability Indices Graphs
Related Window Descriptions
Capability Indices Graph
Capability Indices Graphs
Procedure
- Choose the number of periods that you want to display in the graph by selecting a
number in the No of Points field.
- If you want to view the measurement data used for the calculations for a
specific time period, select the line in the table, right-click and then
click Sample Data. The measurement data used for the calculations
is displayed in the Result column.
- If you want to print the graph, right-click in the
header part of the
Capability Indices Graph window and then
click Print Capability Graph. A message will appear asking you
to confirm. Click Yes. The Report Print dialog box will be
opened. Select the options as required and click OK.
- If you want to print sample data, right-click in
the header part of the window and then click Print Sample Data. A
message will appear asking you to confirm. Click Yes. The
Report Print
dialog box will be opened. Select the options as required and click OK.
Note: It is also possible to print the graph
using the Order Reports window. In the Reports list, click
the Capability Indices and enter the graph number.