Resolve Project Currency Errors
Explanation
If multicurrency budgeting and forecasting or project currency is used
sometimes errors occur if the currency code on the activity connected object is
not present in the currency rate types used for budgeting and forecasting
which is specified in Project Details/Currency tab. In this case calculations
can not be performed for the currencies Base Currency at B&F Rate and/or
Project Currency. By adding the missing currency code to the relevant
rate types the errors can be corrected.
Prerequisites
- Budgeting and forecasting in multicurrency and/or project currency must be
selected on the project
System Effects
- Errors in the Activity/Connections tab for the currency types
Base
Currency at B&F Rate and Project Currency will be corrected.
Window
Project Currency Errors
Related Window Descriptions
Project Currency Errors
Procedure
- Open the Project Currency Errors window, and query for
the
company and project on which the errors should be viewed.
- Right click, click Resolve Currency Errors. A dialog box is
opened.
- Click OK.