Refresh Project Connections

Explanation

Once different types of objects are connected to a project there can be occasions where the cost/revenue and hour values in the object are revised and these revisions may not be reflected on the project connection. Therefore project connection should be refreshed:

This function can be performed for all the the projects in the company when the All Projects checkbox is selected. You can also select the All Objects check box as well which would refresh all the object connections in all the projects. Note that if it is executed for all the projects the operation will run as a background job. 

Prerequisites

System Effects

Window

Project Connection Refresh Runs

Related Window Descriptions

Refresh Project Connections
Project Connection Refresh Details
Project Connection Refresh Runs

Procedure

  1. Open the Project Connection Refresh Runs window and select the Refresh Project Connections option from the right mouse button menu. You can perform this from the Project Connection Refresh Details window which is accessed by the Details right mouse button menu option on the Project Connection Refresh Runs window as well.
  2. Enter the required project ID or select from the List of Values.
  3. Select the object that you want to refresh from the Object Type list. Alternatively you can select the All Objects check box which will refresh all the connected objects that belong to the project.
  4. Click OK.