Create Integration Configuration for Project Data
Explanation
This activity is used to create an integration configuration record for the
project data integration between IFS Applications and Primavera Project
Management (Primavera). Currently, the project data includes the project
calendar, the WBS structure, resource assignments, dependencies and constraints.
The integration of data between IFS/Project and Primavera is described in detail in the
About Integration to Primavera Project Management.
Once integration configurations for project data are created and saved they can
be reused a number of times to perform a project data analysis, or to initiate a
project data export or import.
Prerequisites
- The Primavera Project Management module should be installed.
- A project should exist in IFS/Project.
- An integration setup record should exist in the
Integration Setup/Integration Database Setup tab.
System Effects
- The integration configuration record is created and ready to be used for
exports or imports of project data.
Window
Integration
Configuration
Related Window Descriptions
Integration Configuration/Projects
Integration
Procedure
- Open the Integration Configuration/Projects
Integration tab and create a new integration configuration record.
- Enter a value in the Integration ID field.
- Select a project from IFS/Project to export, or import, in the
Project ID field and select the direction in the Direction field.
- Enter the identity of the project in Primavera that will receive the
exported data, or the one that is to be imported, in the External Project
ID field.
- Select the Project Calendar checkbox if the project calendar in
IFS/Project should be the same in Primavera project. Note that the calendar
must exist as basic data in Primavera, and calendars cannot be imported to
IFS/Project.
- Select the Dependencies and Constraints checkboxes if you
want them to be included in the export or import.
- Select the Resource Assignments checkbox if the resources of the
project are to be assigned to the receiving project during the
export/import. Note that resources must exist as basic data in IFS/Project
and Primavera.
- Enter a valid value in the Setup ID field.
- Enter a value in the Owner ID field.
- Optionally, enter a note.
- Save the record.