Re-initiate Material Demands
Explanation
This activity is used to re-initiate material demands for a maintenance
order to ensure that any changes in the material list for the operation can be
handled.
Prerequisites
- A maintenance order must exist with tasks in the Under Preparation
status.
- Material demands must have been released on the maintenance order, i.e.,
the Material Demand Released check box should be selected.
System Effects
As a result of this activity, all new and updated material lines associated
with the maintenance order operation will be retrieved.
Window
Maintenance Order
Related Window Descriptions
Re-Initiate Material Demand
Maintenance
Order
Maintenance Order/Maint. Order Str.
Maintenance Order/Maint. Order Str./Task Details
Maintenance Order/Included Tasks
Procedure
- Open the Maintenance Order window and
search for the necessary
maintenance order.
- Click the Maint. Order Str. tab.
- In the graphical maintenance order structure, select the task for which
you want to re-initiate material demands, right-click, and then click
Re-Initiate Material Demand. You can also right-click on the
Task Details
sub tab or the Included Tasks tab, and then click
Re-Initiate Material
Demand.
- The Re-initiate Material Demand dialog box opens.
- Select the Keep Reservations and Peggings check box if you want
to keep all existing reservations and peggings for the task.
- Click OK.