Connect
Operations to Separate PM Action
Explanation
Use this activity to plan operation lines, i.e., to plan
crafts and man hours for a Separate PM action, e.g., a mechanic to perform the action, and how many hours it
will take. An operation can be performed by
a single employee or many employees.
Furthermore, you can specify a particular team
that should be in charge of the operation. When a team is defined, you can only
specify employees that belong to the particular team.
Prerequisites
-
Maintenance organizations, employees and maintenance teams must be defined in the
Organization Basic Data window.
-
Crafts should be entered and connected to sales parts (applicable only to IFS/Service Management) in the
Organization Basic Data
window.
- Jobs must have been defined on the
Jobs tab prior to connecting the operation to the PM action if the operation is to
be connected to a job.
System Effects
As a result of this activity, an operation line will be
connected to the PM action.
Window
Separate PM Action
Related Window Descriptions
Separate PM Action
Separate PM
Action/Operations
Procedure
- Open the Separate PM Action window,
and query for an existing PM action.
- Click the
Operations
tab.
- Create a new record (F5).
- Enter a value in the Operation No field.
- Enter the maintenance organization that is in-charge of
the operation, and the craft required for the operation in the Maint.
Org. field and the Craft field respectively. Use the List of Values to
select a suitable value.
- Enter the number of men required for the operation
in the Planned Men field, and the number of hours required in the Planned
Hours field.
- Specify the site and the ID of the maintenance
team in the Team Site and Team ID fields if you want the
operation line to be performed by members of a particular maintenance team. Use the List of Values to select a suitable value.
- Organize the operation lines according to the jobs if
required. Operation lines can be connected to the jobs using one of the
following methods:
- Enter a value in the Job ID field of
the particular operation line.
- Click the
Separate PM Action/Jobs
tab. Create a new job or select one from the available list and save.
Select the job entry and create a new operation in the lower table.
- Create an
operation first (steps 1-7 and 9-11). Once you have created the
operation, click the
Separate PM Action/Jobs
tab. Create a new job or select one from the available list. Right-click
on the lower table and then click Connect Existing Operations. The
Connect an Existing Operation dialog box opens. Enter the
operation number in the relevant field. Click List to select a
suitable value. Click OK.
- Enter the sales part site and the sales part number if
you want to invoice the price of the operation to a customer (only
applicable to IFS/Service Management).
- Enter information about any special equipment required
for the operation in the Equipment Needed field, and any other optional
information in the Remark field.
- Save the information (F12).