Reschedule Shop Order (Operation)

[About Manufacturing Visualizer] [About Visualization for Machine Availability] [About Visualization for Labor Availability] [About Shop Order Infinite Scheduling]

[To Manufacturing]

Usage

Use this dialog box to trigger a rescheduling of shop order operation(s).

When rescheduling to an earlier date, scheduling will be based on the given Finish Date. The last available work date/time before the date/time where operation was released will be automatically proposed, but can be manually edited.

When rescheduling to a later date, scheduling will be based on the given Start Date. The first available work date/time from the date/time where operation was released will be automatically proposed, but can be manually edited.

Note: New start and finish date will be based on the infinite scheduling logic and may differ from the value seen in the dialog box. For instance, if the provided new start date is on a non working date, the operation will receive a new start date corresponding to the first available work date/time from the values.

Activity Diagrams

Handle shop order

Activities

Reschedule shop order operation using drag-and-drop