Evaluate RRP Results using Graph and Period Template

Explanation

Use this activity to study a bar graph of the workload for a specific work center and period template during a specified interval of time. You also can study the workload for different master schedule sets, since these can have different forecasts. In this way, you can see how different forecasts burden the work centers. The workload shown in the graph is divided per master schedule set. You specify this when you select the work center whose workload you want to view. If you work with dynamic periods, specify the site from which you want to retrieve the periods. This does not mean that workload is displayed per site. If a work center is used by several sites in the same master schedule set, the total workload for all sites is displayed.

Note: Regardless of the period unit, the system does not consider the site where the workload originates, since master schedule sets are not site-dependent.

Prerequisites

This activity requires that the calculation of RRP must have been performed.

System Effects

There are no system effects as a result of performing this activity.

Window

RRP Load per Work Center

Related Window Descriptions

RRP Load per Work Center

Procedure

  1. In the Work Center No field, enter or query for the work center you want to view. You then see the workload in the specified time interval. When you select the work center, you also select the master schedule set and site.
  2. In the Period Unit list , specify that you want to view the workload by dynamic periods.
  3. In the Select Period Template dialog box, select the template by which you want to study the workload. Use List to select from the available templates.
  4. In the From Period and To Period fields, enter the required values.
  5. If you change the values in any of the fields, click Refresh Graph to update the graph.