Define Period Unit Calendar
Explanation
Use this activity to define the period calendar to be used in the system. A
record must be created for each period in a year for which planning is done. You
can define the forward planning by different period units, which means that you can
have daily, weekly, monthly, or quarterly periods defined for the same year.
Prerequisites
There are no prerequisites for this activity.
System Effects
As a result of this activity, the system creates a period unit calendar for use within
the system.
Window
Planning Period Units
Related Window Descriptions
Planning Period Units
Procedure
- Open the
Planning Period Units window.
- To create a calendar automatically, right-click and then click Create ISO Weeks.
- You also can create the periods manually by selecting New. The following steps
are valid only if you decide to create the periods manually.
- In the Plan Year column, specify the year to which the period should belong.
- Enter a number for the period in the Plan Year Period No field. You also can provide a
description for the period in the Plan Period Description field.
- In the Plan Period Unit list, select the unit corresponding to the
period.
- Repeat steps 3 to 6 for each period you want to define.
- Save the record.