Update Routing Revision and/or Alternative
Explanation
This activity is used to select a different routing revision and alternative for the shop
order. (The current operation list is automatically selected when the system registers the
shop order.) If the selected shop order is in the Parked status and the status before
Parked was Reserved or Started,
only the revision and/or alternate on the shop order head will be changed. If
the shop order is for a part that has lot size based routing revision you can
change to the correct alternative for the shop order lot size if the shop order
is in the Planned or Released status.
Note: For a shop order that was in the Reserved or Started
status before the Parked status, all updates on the Shop Order/Operation tab have to be done manually.
In some instances, update is also possible to be done in the the Compare Shop Order with Structure and Routing window.
Prerequisites
This activity requires that the shop order is in the Planned or Released
status or the shop order in the Parked status with the Enable Rev/Alt to be Changed check box selected.
System Effects
- The revision and/or alternate on the shop order head gets changed.
- If the shop order is in the Planned or Released status, the load is changed due to the new routing revision and/or alternate.
- If the part is a configured part and the shop order is in the Planned or Released
status, the Shop Order/Operation tab will be updated with the rules for the selected revision and/or alternate.
Window
Shop Order
Shop Orders
Related Window Descriptions
Shop Order
Shop Orders
Update
Operation and Alternative
Procedure
- Open the Shop Order or Shop Orders
window.
- Query for the record.
- Right-click, point to Update Allocations and/or Operations, and
then click Update Routing Revision and/or Alternative. The
Update Operation and Alternative dialog box
appears.
- Select the desired routing revision and alternative combination in the
Revision field. Click List to select from available valid
combinations.
- To change only the alternative, select the specific alternative in the
Alternative field.
- Click OK.
For a shop order with a lot size based routing revision
- Open the Shop Order or Shop Orders
window.
- Query for the record.
- Right-click, point to Update Allocations and/or Operations, and
then click Update Routing Alternative for Lot Size.