Define Tool Instance
Explanation
Use this activity to enter and maintain records of tools and instances of
tools. Tool IDs can be linked to routings
to specify particular tools to use. Tool instances can be used by IFS/Constraint
Based Scheduling as part of a shop order operation capacity used to schedule
shop orders. Tool Instances have effectivity date ranges that define the
availability of each tool instance to production.
Prerequisites
This activity requires that a tool ID must have been defined in
Manufacturing Tool.
System Effects
As a result of this activity:
- A new tool
instances for a tool is created.
- This tool instance can be used by CBS, if installed, as part of a shop
order operation capacity used to schedule shop orders.
Window
Manufacturing Tool
Related Window Descriptions
Manufacturing Tool
Procedure
- Open the Manufacturing Tool window.
- Populate the window and select the tool ID to connect with new tool instances
in the Tool ID field, or query for the tool ID.
- In the
Tool Detail tab, either use the default tool instance
displayed in the Tool Instance field to make modifications, or click
New to
create a new instance.
- Enter the tool instance name you want to create in the Tool Instance column.
- Enter a description of the tool instance in the Description column.
- If desired, enter any notes about the tool instance in the Note Text
field. Double-click in this field to open the Note Text editor to simplify
entering extensive text.
- If an equipment object is used, connect it with the tool instance in the Object ID
column. Click List of Values to select from the available object IDs.
- If desired, specify the work center in which the tool instance is normally
found. Click List of Values in the Normal Work Center No field.
- If desired, specify the production line in which the tool instance is
normally found. Click List of Values in the Normal Production Line
field.
- If desired, enter the date in the Last Calibration Date field that the
tool instance was last calibrated. This must be on a calendar working date.
The date in the Next Calibration Date field will automatically be
calculated.
- If the tool instance uses Measurement System Analysis (MSA), enter
necessary values in the appropriate fields.
- Specify the validity range of the tool ID instance in the Begin Date and
End Date
columns. You do not need to specify an end date.
- Repeat steps 2 - 6 for each tool instance.
- Save the record (F12).