Calculate Cumulative Lead Time

Explanation

Use this activity to calculate a part’s cumulative lead time. The cumulative lead time of a part is the total turnaround time for all parts in the structure. You can calculate the cumulative lead time for a single part, or all parts for the specified site.

Prerequisites

A part must have been defined with a routing.

System Effects

As a result of this activity:

Window

Cumulative Lead Time Calculation

Related Window Descriptions

Cumulative Lead Time Calculation

Procedure

You can either calculate the lead time directly (Procedure A), or schedule the task as a background job (Procedure B).

Procedure A:

  1. Open the Cumulative Lead Time Calculation dialog box.
  2. In the Site field, select the site for which you want to run the calculation. Click List to select from the available sites.
  3. If you want to calculate the cumulative lead time for a specific part, select the part in the Part No field. Click List to select from the available parts. If no part is selected, the calculation is done for all parts in the site.
  4. Click OK.

Procedure B:

  1. On the Cumulative Lead Time Calculation dialog box, click Schedule. The Create New Task Schedule window opens.
  2. Set the relevant scheduling parameters and Save. You can view the scheduled tasks in the Scheduled Database Tasks window.