This activity is used to adjust the budget values for one
or more vehicles included in the operational budget. When you define a new
budget, the budget value for the year will automatically be divided and
distributed evenly over the twelve months. These monthly budget values are then
distributed evenly over all the vehicle parts.
Observe the following example:
An operational budget with a budget value of 75,000
engine hours (EHR) is created for a given year. This budget value is calculated
by the system, and the
Budget Month tab will display
6250 EHR every month.
Assume you have two vehicles, for instance, AIRCRAFT 747 and AIRCRAFT
743, belonging to the given part number and owner combination. The monthly
budget value of 6250 EHR is divided by the number of vehicles, and each vehicle
on the
Vehicles tab will automatically receive 3125 EHR as the
budget value for the year. During the month of January, suppose AIRCRAFT 747 will
run an additional 100 EHR. This 100 EHR will be deducted from the budget
for AIRCRAFT 743 and added to AIRCRAFT 747's budget for the month of January.
The new budget values for the month of January on the two vehicles are as
follows: 3225 EHR (AIRCRAFT 747) and 3025 EHR (AIRCRAFT 743).
The budget value for the vehicle can be updated, provided that the budget values have not been approved and the total value after the adjustment equals the existing yearly budget value. This will prevent any errors been generated when the budget is approved.
To perform this activity, the budget for the relevant month should not have been approved, i.e., the budget month should be in the Not Approved status.
As a result of this activity, the utilization of vehicles per month will be adjusted in accordance to the operational budget.
Follow this procedure to adjust the budget value of a vehicle for selected months