Remove a Task
Explanation
Use this activity to remove one or more tasks from a
work scope. Ideally, this activity can be performed to remove unwanted tasks
ahead of the release of a work scope.
Prerequisites
- The Task Not Applicable check box must not be selected for the
task.
- Shop orders are not created by releasing interim orders.
System Effects
As a result of this activity, the task is removed from the work scope and the
status of the task is changed to Removed.
Window
Define Work Scope
Task Summary
Change Work Scope Tasks
Related Window Descriptions
Define Work Scope
Define Work Scope/Work
Scope Tasks
Define Work Scope/Define Work Scope/Affected Part Tasks
Task Summary
Task Summary/Modification
Change Work Scope Tasks
Change Work Scope Tasks/Modification
Procedure
Follow this procedure to remove a task from the work
scope:
Note: You can also use the
Change Work
Scope Tasks window to remove tasks from a work scope.
- Open the Define Work Scope
window.
- In the Work Order No field, query (F3) for
the work order to which your work order part belongs.
- Click the
Work Scope Tasks tab to
verify the task you intend to remove.
- Right-click anywhere in the header of the
Define Work Scope window, and then click Task Summary.
The Task Summary window opens. (If preferred, select the
relevant right mouse button option to open the
Change Work Scope Tasks
window.)
- Click the Modification tab.
- Select the All Running option. The table in
the window will display all running tasks for the modification.
- Clear the Include In Workscope check box
for the tasks you want to remove from the work scope.
- Save the record (F12).
- Right-click on the header of the Task
Summary window, and then click Define Shop Visit Work Scope.
The Define Work Scope window opens with the
relevant details.
Alternatively, if you already have the
Define Work Scope window open, simply refresh the data (i.e., in the Work Order No
list, re-select your work order) to incorporate the new changes.
- Click the
Work Scope Tasks tab to
view the tasks that are removed from the work scope. The status of the task
is automatically set to Removed (as illustrated in the State field).