This activity is used to add one or more modifications to a work scope. Usually the mandatory modifications, due modifications and modifications included in the customer baseline (i.e., those which have not been complied with as yet) are transferred to the work scope. Apart from the required modifications and due modifications, you can choose the modifications you want added [or not] to the work scope. For instance, if a modification which is not due nor assigned to a serial exists, and this modification is applicable to a particular serial, you can choose to add [or not add] the modification to the work scope, as per your requirements.
When you want to manually add modifications to the work
scope you need to select the All Not Complied option to populate
the table in the window with modification records for which the Include in
Work Scope? check box can be modified.
To view all modifications for the serial structure irrespective of whether the
modifications have been complied with or not, select the All option. To
only view the modifications that have been complied with select the All PCW
option.
If you want to create a de-comply task(s) select the All option or
the All PCW option. Note: A de-comply task must be created before
the modification can be added to the work scope.
To view modifications that are currently included in the work scope and/or, if
required to remove modifications from the work scope, select the All Running
option.
Task Summary/Modification
Shop Visit/Visit
Defaults/Modification Baseline
Define Work Scope/Work
Scope Tasks
Define Work Scope/Define Work Scope/Affected Part Tasks
Use the following procedure to add a task to the work scope:
- Open the Define Work Scope window, and query (F3) for your work order (selected in step 2 of this procedure).
- Click the Work Scope Tasks tab. Here, you can view information for the modifications you have selected to include in the work scope.
Use this procedure to create a decomply task to be included to the works cope at a later date: