Calculate Cost for Part Cost Group
Explanation
Use this activity to calculate costs for all parts connected to the same part cost
group. This
optional but recommended task is to be performed by a system administrator or
equivalent person.
You can calculate costs for several parts at a time. When calculating costs, the costs set up
throughout the system are gathered and
attributed to the correct part. A cost calculation can be performed for a part
cost group. The calculation of all parts is performed as a batch job. The
calculation updates the part's level labor costs and the cumulative costs in the
estimate section of the inventory part register. The structures and operations
of the part are calculated and the costs are rolled up to update the cumulative
calculations of the parent part.
Note: You cannot perform cost calculation for cost set 1.
Prerequisites
This activity has the following prerequisites:
- Cost sets must be defined.
- Sites must be defined.
- Inventory parts must be created.
- The cost set for which you are performing the calculation must have costs defined.
- Parts must have been assigned to the selected part cost group.
System Effects
As a result of this activity:
- The costs for all parts connected to the part cost group all
levels deep will be calculated and the results saves in the selected cost set.
- The calculations are used in the comparison of accumulated (all level)
costs.
Window
Part Cost Group
All Parts Cost
Calculation
Related Window Descriptions
Part Cost Group
All Parts Cost Calculation
Procedure
You can perform this activity in the
All Parts
Cost Calculation window by either direct execution (Procedure A) or by
scheduling the task to execute as a background job (Procedure B).
Procedure A:
- Open the All Parts Cost Calculation
window.
- In the Site field, click List and select the site for which
you want to perform the cost calculation, from the List of Values.
- In the Cost Set field, click List and select the cost set
for which you want to perform the cost calculation, from the List of Values.
- In the Part Group ID field, click List and select the part
cost group for which you want to perform the cost calculation, from the List
of Values.
- In the Effective Date field, specify the date when structures and routings should be
valid.
- In the Stop Roll list, click either Not Stop Cost Rollup or
Stop Cost
Rollup.
- Click OK.
Procedure B:
Click Schedule, it will open New Database Task Schedule
window. Set the scheduling parameters as desired and save.
To perform this activity in the
Part Cost Group
window, follow these steps:
- Open the
Part Cost Group window.
- In the Part Group ID list, query for the part cost group for which you want to perform
the calculation.
- In the header, right-click and then click All Parts Cost Calculation. The values from the selected part cost group will be shown in the
All Part Cost Calculation window.
- In the Cost Set field, click List and select the cost set
for which you want to perform the cost calculation, from the List of Values.
- Click OK.