Assign Cost Buckets to Cost Template
Explanation
Use this activity to assign the cost buckets of your choice to a new cost template.
Prerequisites
- A cost template must have been created.
- Cost buckets must have been defined.
System Effects
This activity will assign the cost buckets of your choice to the selected cost
template.
Window
Cost Template
Related Window Descriptions
Cost Template
Cost Template/Cost Template
Procedure
- Open the
Cost Template window.
- In the Template list, select the cost template that you want to use as a
source for the new cost template.
- Click the
Cost Template tab and create a new record.
- In the Bucket ID field, select the cost bucket you want to assign to the cost
template. Click List and use the List of Values to select from available cost buckets.
- If you want to use this cost bucket for capturing manufacturing level
cost, select the Manufacturing Cost check box. This is valid for the cost
rollup process as well as for the shop order costing flow.
Note 1: If
you want to capture Material Overhead cost for sub-assemblies, you should
enter a Material Overhead cost bucket for which the cost element source ID
is 500 (Total Cost). Then select the Manufacturing Cost check
box. Ignore the warning message. The Material Overhead cost will show up as
level cost at the parent level.
Note 2: If you want to capture Material Overhead for purchased parts
which use the weighted average inventory valuation method or where the
inventory part cost level is set to Cost Per Serial, you should enter
a Material Overhead cost bucket for which the cost element source ID is 500
(Total Cost). The Material Overhead cost will show up as level cost at the
parent level.
- If you want to use this cost bucket for capturing external acquired cost,
select the External Acquired Cost check box. This is valid for the cost
rollup process as well as for the purchase order arrival process (capturing
Delivery Overhead cost).
- If you want to, you can change the default cost types values in the Sunk/Relevant Cost,
Direct/Indirect Cost, or Fixed Variable Cost columns. You can also change the Bucket
Frequency. Changing any of these values will cause the Override Flag check box to be
marked.
- Repeat steps 3-7 for each cost bucket you want to assign.
- Save the changes.