Reopen Contract Change Order

Explanation

Use this activity to reopen a contract change order to make it possible to change or add information if it e.g. has been rejected. When you have set the status to Analyzed most of the information cannot be changed. The only way to add or update this information is to first reopen the contract change order so the status is reversed to Analysis in Progress and then do the necessary changes.

Prerequisites

System Effects

Window

Contract Change Order

Related Window Descriptions

Contract Change Order

Procedure

  1. Open the Contract Change Order window and query for the contract change order that should be reopened.
  2. Right click and and click Status, and then select the Reopen menu option.
  3. Click Yes to the question about if you want to continue to set the contract change order to the Analysis in Progress status.
  4. Click Yes to the question about if you want to continue when the approval routing steps, approved dates and rejected dates will be cleared.