This activity is used to register resource requirements for a task card or subtask.
Resource planning on task cards and subtasks is done on the resource group level. This means it is possible to plan groups of persons with the required competency to perform the work and groups of tools or equipment that will be used during the work. For example, a rail engineer is required to inspect the brake system of a locomotive, and will require a test gauge to check the air pressure. Resources with following settings can be planned on task cards and subtasks:
It is possible to plan multiple person groups and tool/equipment groups on a task card or subtask.
Task Card
Subtask
Task Cards per
Maintenance Code
Modification
Details
Condition
Monitoring Program
Task Cards
per Fault Function
Serial Part Revision
Post
Maintenance Check Definition
Task Card/Resources
Subtask/Resources
Task Cards per Maintenance
Code/Resources
Modification Details/Execution
Type Info/Resources
Condition Monitoring
Program/Condition Category Info/Resources
Task Cards per Fault
Function/Resources
Serial Part Revision/Life
Limit/Resources
Post Maintenance Check
Definition/Part Revision Info/Resources
Use the following procedure to register resource requirements for a task card:
It is also possible to register resource requirements in the following places. To do this, navigate to the relevant tab, select the required task card revision and continue with steps 3 - 8 listed above:
- Task Cards per Maintenance Code/Resources
- Modification Details/Execution Type Info/Resources
- Condition Monitoring Program/Condition Category Info/Resources
- Task Cards per Fault Function/Resources
- Serial Part Revision/Life Limit/Resources
- Post Maintenance Check Definition/Part Revision Info/Resources
Use the following procedure to register resource requirements for a subtask: