Create Work Tasks
Explanation
This activity is used to add and modify the work tasks required to complete a work order.
If the work should be executed by different maintenance organizations,
and different objects you may consider dividing the work into multiple work tasks. At creation,
the work task will receive the New status.
Work tasks can be planned on any of the sites that belong to the same company
as the work order (provided the user is connected to the site).
On each work task you can enter a description, long description, maintenance
organization, duration, reported/actual object. You can also enter a planned
start and planned finish dates, to indicate when the work task should be
executed.
If there is a need to invoice the customer (service order) through work task,
customer should be defined for the work task.
When Fleet and Asset Management is used,
work tasks and subtasks will be connected to the work order at the time the
maintenance order is released. These work tasks and subtasks will receive the
New status automatically. The New work task status is intended for
allocation of resources at an early stage of the process for preparing a work
order.
Prerequisites
- Sites, Maintenance organizations, Maintenance teams must have been defined
and connected to each other.
- If you are using IFS/Service Management, information on customer and service
contracts must have been defined.
- If the work task is to be connected to a job, the jobs must be defined on
the
Jobs and
Templates tab prior to connecting the work task to the work
order.
System Effects
As a result of this activity, work tasks with the
status New will be connected to the work order.
Windows
Work Task
Prepare Work
Order
Work Order StructureRelated Window Descriptions
Work Task
Work Tasks
Prepare Work Order
Prepare Work Order/Work Tasks
Prepare Work Order/Jobs and Templates
Work Order Structure
Work Order Structure/Work Tasks
Procedure
Option 1: Use the Work Task or the
Work Tasks
window.
- Create a new record (F5).
- Select a work order to which the work task need to be created.
- In the Order No. field, enter a unique number
for the order of work tasks. Optionally, you can leave
this field blank and a value will be assigned automatically.
- Enter a description about the work in Description field.
- Work Order site is displayed in the Site and Maint Org Site
fields. If the work is performed in another site change the value in
Maint. Org. Site field. Use the List of Values
to select another site to which the user is connected, if appropriate.
- Enter value in Maintenance Organization field, if appropriate.
- Reported Object ID will be inherited from work order if Object
ID is defined in work order. Use the list of values to change it, if
appropriate.
- Enter value in Actual Object ID field if the fault need to be
fixed in another object than the reported object. Note: Actual Object ID
can be modified during the progression of the work task as well.
- Enter the site and the ID of the maintenance
team in the Maint Org Site and Team ID fields if the work task need
to be performed by members of a particular maintenance team.
Use the List of Values to select a suitable value.
- Enter value in Duration field, if appropriate. This represents
the time that is required to execute the work task.
- Enter the Customer No if there is a need to invoice the customer for the
services provided through the work task. (only applicable for IFS/Service Management).
- Organize the work tasks according to the jobs if
required. Enter a value in the Job ID field of
the particular work task.
- Enter a date interval for the work task, if appropriate.
- Enter the task card type and location (only applicable for Fleet and
Asset Management). Use
the List of Values to select a suitable value.
- In the Internal Remark field, you can enter
internal information on the work task. This can be, for instance, handover
information between shifts.
- Save the information (F12).
Option 2 : Use the Prepare Work Order
, Report In Work Order
, Prepare Work Order Quotation/Prepare or
the Work Order
Structure window.
- Query for a work order to which the work tasks are to be added.
- Select the Work Tasks tab.
- Follow the Steps from 1-16 as Option 1, if appropriate.