Change Finish with Task

Explanation

This activity is used to change the setting of a work order's Finish with Task indicator. The Finish with Task setting is to be set (to true) to automatically perform the closure of the work order.

The action Finish with Task is available by RMB in Prepare Work Order and Work Order Structure windows and available in Aurena by command button Change Finish with Task in Prepare Work Order and Work Order Structure Navigator.

Prerequisites

System Effects

Window

Prepare Work Order
Work Order Structure

Related Window Descriptions

Prepare Work Order
Work Order Structure

Procedure

Use the following procedure to change the setting using either the Prepare Work Order or Work Order Structure window.

  1. Open the desired window.
  2. Query for the work order. (F3)
  3. Right-click on the top part of the window, click Finish with Task.