View Calculated Progress
Explanation
This activity is used to graphically view the work progress of work orders in
the work order structure.
Once the progress of work is calculated on a work order, the activity bar for
the work order in the Gantt will be updated to show the progress.
Prerequisites
To perform this activity, progress must have been reported on the work order.
System Effects
As a result of this activity, it is possible to graphically view how much of
the work has been completed.
Window
Work Order
Structure
Related Window Descriptions
Work Order Planning Gantt
Work Order Structure
Procedure
- Open the Work Order Planning Gantt window and query (F3)
for the necessary work order.
- Observe the progress shown in the relevant activity bars. Progress is
shown by a Black-and-White striped bar within the activity bar for a work
order. Note that this is not visible for grouping work orders.
- The actual value of progress is shown in the tool-tip for the activity
bar if the Progress (%) check box is selected (in the Tool Tip
Properties dialog box).