Start Work Assignment

Explanation

This activity is used to start the work assignment, by the assignee. It is considered as the clock in point of the assignment to count the execution time.. Once started the assignment, assignee can either set it to completed, incomplete or pending completion states depending on the execution progress.It is still possible to cancel a started assignment.

Prerequisites

System Effects

As a result of this activity the work assignment is set as as Started.

Related Window Descriptions

N/A

Procedure

Use the following procedure to start an accepted work assignment.

  1. Open the Subcontract Work Orders > Execute Work Lobby Page.
  2. Find the Lobby section for Assignments.
  3. Click on the Accepted or All Assignments Counters to list all accepted work assignments.
  4. Select one or more accepted work assignment lines and click on Start Work command button at the top of the lines.
  5. Observe the Change of status.